MPAH – Project Brief Update

MPAH – Project Brief update as at 20-12-2018.

Efforts are being made to wrap up works on all final beams to prepare MPAH towards roofing. 

1. Substructure works – 80% completed.  

2. Superstructure works.
a. Ground floor columns/beams – 85% 
b. First floor columns/beams – 50% 
c. Second floor columns/beams – 50% 

Superstructure progress – 30%